The project is the middle of a long-term project when a major error is discovered by the develop team. This error can be fixed by implementing a large change to the scope of the project. This change could influence both time and budget plans. What should the project manager do first?
A、Analyze the change request and present it to the change control board.
B、 Implement the change request and inform the stakeholders afterwards.
C、 Implement the change request and present it to the change control board afterwards.
D、 Analyze the change request and present it to the steering committee.