試題內容



The project manager has recently been appointed to an ongoing software development project. The stakeholder considers that the project is on schedule and budget according to the previous project manager’s reports. During the new project manager reads the relevant project’s documents, he knows the project schedule delay and over budget. What the project manager should do?
A、Efforts to fast track the progress of the project in order to meet demand
B、 Report to stakeholders to assess the situation
C、 Use of existing resources to continue to run the project
D、 Meeting with stakeholders and apply more resources