試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-3
考試中心《信息系統(tǒng)項目管理師-pmp練習題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

In an eight-month project, the customer requests a change to a complex business requirement. Development is 72% complete. The customer suggests the project schedule be extended by an additional month. What should the project manager do next?
A、Reject the change since most of the development is complete.
B、Ask for additional funds.
C、Analyze the variance.
D、Accept the change since the customer has increased the schedule.